Why is it recommended that a contractor visit the work site frequently?

  1. To know when to schedule final payment

  2. To keep the subcontractors informed of the job's progress and to check on what materials must be ordered for the next phase

  3. To know when to schedule float time

  4. To know the approximate final cost

The correct answer is: To keep the subcontractors informed of the job's progress and to check on what materials must be ordered for the next phase

Visiting the work site frequently is essential for a contractor to effectively manage the job's progress. By being present, the contractor can provide updates to subcontractors about the current state of the project, ensuring that everyone is aligned with the timeline and any changes that might have occurred. This direct oversight helps the contractor evaluate how work is progressing and what needs immediate attention or adjustment. Furthermore, by closely monitoring the site, a contractor can determine what materials are required for the next phase of work. This proactive approach enables timely ordering and delivery of materials, preventing delays in the project that could arise from waiting until the last moment. Regular site visits also empower the contractor to anticipate potential issues, verify that work meets quality standards, and facilitate effective communication among team members. Thus, maintaining a hands-on approach significantly contributes to the overall efficiency and success of construction projects.